Description | Date | Week(s) |
---|---|---|
Update | 26.06. - 07.07. | 26-27 |
Scratch book
26.06 Monday
Developers focused on writing test cases, conducting testing, and working on assigned tickets.
27.06 Tuesday
Testers continued testing activities and developers wrote additional test cases to ensure comprehensive coverage.
Mobile UI at the moment:
28.06 Wednesday
The team conducted further testing and front-end development. They also attended a practical testing lesson and hosted an after-lab event.
29.06 Thursday
Frontend developers worked on implementing hover effects on layers, updated test cases, and created new ones. They also participated in an after-lab event.
30.06 Friday
Frontend developers continued working on layer highlighting functionality, updated test cases, and attended a practical testing lesson. Travis got re-rebranded as Tukko ("clog"). So from now on we will refer to the project as Tukko.
We improved our branching still. One long-running branch was finally merged.
It was our turn to arrange the After Lab! We went to the Viitaniemi Archery field to do archery with Jyväskylä Academy of Historical Martial Arts.
03.07. Monday
GitLab pipeline updated and tested. Modal for the data analytics dashboard was designed for the front end. We tried things with Git branching like Feature Branch - Staging - Main. On the testing side there was learning backend and load testing with JMeter. NodeOn company kept a lecture about CVs and company recruitment.
We got a new logo for Tukko.
04.07. Tuesday
Further JMeter practice and test case making from the testers. The back-end side got a lot of new additions. The modal dashboard got new styling for the front-end, and it was integrated into popup markers. In the afternoon we attended a social engineering lecture by Riku Juurikko.
UI at the moment:
Different colors were tested on the new markers:
Of course, fooling around with the settings.
05.07. Wednesday
The first demo for Tukko modal data analytics dashboard with graphs was made. Also, a drop down list, radio buttons and a popup view were implemented. Possibilities for data analytics options were researched. This day we started implementing our own backend data instead of just static data. On the testing side more JMeter, more test cases. The front-end got dark mode Geoman buttons.
Dark mode tests:
Tooltips UI but now yet showing info.
06.07. Thursday
Documentation got long-awaited updates. Sites CSS got a clean-up. The Feedback form visuals got updates on dark mode. The backend and front-end got further improvements with full-stack connectivity. Statics datasets were created for the data analytics dashboard and they were implemented to the graph. Fetch limit logic was improved for mongoDB with insert time check.
Tooltip now shows actual data.
And improvements.
07.07. Friday
Istekki's representatives came to tell about their company. After the lecture, we showed them our code bases and discussed bout our team dynamics and work flow. Documentation got a lot of fixes and content. The modal dashboard got modified. A new route /tms/station/:id
for station sensors analytics was added. Backend fetch logic got improved. Getting the backend running on our CSC instance proved to be a lot of work. In the afternoon we enjoyed the sunny weather and kept sprint 04 review outside.