Current Status

Gitlab Board and issues

Status of Sprint 04 Date 7.7.2023

What has been achieved

  • All features of Skill Collector 1.0 are ready

Problems / challenges

  • Putting Skill Collector in Mysticons service causes a bit of problems
  • End users are still little confused about using Skill Collector

Next steps

  • Testing & acceptance
  • Getting Skill Collector to production service provided by Mysticons
  • Bug fixes
  • Preparing for release
  • Documentation

Status of Sprint 03 Date 22.6.2023

What has been achieved

  • FEA-47-answers-database implemented & tested
  • Power Automate almost ready, needs to be tested

Problems / challenges

  • The tester is constantly finding bugs :)

Next steps

  • Power Automate flow testing
  • Project progress according to the RoadMap

Status of Sprint 02 Date 8.6.2023

What has been achieved

  • Mock up ready
  • The backend of the old Skill Collector has been studied, and an attempt has been made to preserve as much of it as possible. Now the backend of Skill Collector 1.0 is ready, but changes are expected.
  • We have prepared well for the Open Doors event and the team is ready to present the project

Problems / challenges

  • The biggest challenge is that the team members have no experience coding with Vue.js, so it takes time to practice

Next steps

  • We start to code the frontend according to the mock up, and to improve the usability of the Skill Collector.
  • We start testing to get bugs fixed

Status of Sprint 01 Date 26.5.2023

What has been achieved

  • A good idea of ​​the improvements to Skill Collector and what we plan to do with the product
  • Use Cases and the big picture of the product and its connections to other products

Problems / challenges

  • The challenge is to connect the Skill Collector to the new Skill database, and change the operation of the old Skill Collector to meet the new requirements

Next steps

  • Preparation for Open Days
  • Creating a roadmap

Status of Sprint 00 Date 19.5.2023

What has been achieved

  • Orientation to the project
  • Getting to know the team
  • Getting to know the assignment
  • Fixing up workstations
  • Orientation to working at Wimma Lab

Problems / challenges

  • A complete understanding of the assignments is still in progress, but we need to get the documentation running, and we are starting the project planning

Next steps

  • Project plan
  • Requirement specification